NOTE:
This technical manual is based upon the outdated API Specification 4E,
which has been superseded by API Specification 4F, June 1995. The API RP
4G provides a "Recommended Guyline Anchor Spacing and Load
Chart." AESC has published "Guidelines on the Stability of
Well Servicing Derricks." There has been considerable progress
within the industry to design procedures to assure the integrity of the
stability system without the necessity of conducting individual pull
tests on each of the anchors.
SECTION IV: CHAPTER 1
OIL WELL DERRICK STABILITY: GUYWIRE ANCHOR SYSTEMS
- INTRODUCTION.
Work-over rigs are mast type devices that vary significantly from
crane or other boom (mast) type equipment. Work-over rigs experience
constant and varying dynamic loading conditions. They are subjected
to various compression forces, along with jarring and wind loading.
Other forces induced by pipe, tubing, etc. being stacked in the
derrick and workers aloft on the derrick platform, as well as an ever-changing
number of lateral and vertical forces are also present. Because of a
work-over rig's dynamic environment, the health and
safety of the operation is dependent upon the stability of the rig
and its guy anchor system.
- CAUSAL FACTORS.
- There is no specific OSHA standard that addresses
the stability of derricks in the oilwell drilling
and servicing industry (Figure IV:1-1).
But because of the fatality record there is a need
for a guideline detailing the type of temporary
stability systems according to the type of soil and
its holding capacity, methods of installing guywire
anchors, integrity of the system, and acceptable
parameters in lieu of actual pull testing should be
established.
- Investigation into each fatal incident has
determined that the cause of the upset was component
failure rather than total system failure. This
clearly illustrates the fact that the integrity of
the system is no sounder than its weakest component.
|
FIGURE
IV:1-1.
OILWELL
SERVICING
DERRICK.
 |
- INDUSTRY RECOMMENDATIONS.
- The American Petroleum Institute (API) in its
Specification 4E "Specification for Drilling and Well
Servicing Structures" sets forth a "Recommended
Guying Pattern General Conditions." The Association of
Oilwell Servicing Contractors (AOSC), in its publication Recommended
Safe Procedures and Guidelines for Oil and Gas Well
Servicing, recommends the same guying patterns as are
set forth in API Specification 4E.
- Though not present in the AOSC publication, the API
Specification 4E provides a "Recommended Guyline Anchor
Spacing and Load Chart." This is discussed in detail in
the Guidelines on the Stability of Well Servicing Derricks.
There has been considerable progress within the industry to
design procedures to assure the integrity of the stability
system without the necessity of conducting individual pull
tests on each of the anchors.
- APPLICATION. This chapter is
intended to form the basis of a minimum safety guideline, for
the use of Temporary Guywire Anchor Systems on derricks, in the
oil well drilling and servicing industry. Recommended
procedures, practices, equipment, and requirements have been
developed based on availability, capability, adaptability,
dependability, and reliability of the various types of systems.
- TYPES OF GUYWIRE ANCHORS.
- MANUFACTURED ANCHORS.
- There are four basic types of manufactured anchors: the
screw or helix anchor, the expanding plate anchor, the flat
plate anchor, and the pivoting anchor. Holding capacity of
these anchors varies; detailed information on holding
capacity, comparison charts with illustrations, and
characteristics specific to each design may be found in
Section 2 of the support manual.
- When installed in conformance with manufacturer
specifications and evidence thereof is provided, this would
satisfy the requirement for individual pull testing.
- Screw(helix)-type anchors have a direct correlation
between anchor capacity and the torque required to install
the anchor. Following the manufacturer's specific
recommendations as to torquing, with proof thereof, is a
valid method of determining anchor holding capacity.
Torquing according to manufacturer's specifications is an
acceptable nonpull-test method of determining
anchor capacity.
- SHOP-MADE (IN-HOUSE FABRICATED) ANCHORS.
These anchors should be designed by a registered engineer and
conform to accepted engineering practices. Written procedures
shall be established for installation. These manufactured
anchors should be proof tested for structural integrity and
holding capacity. Records shall be maintained of test protocols
and holding capacity based on soil type. Individual pull testing
will not be required if anchors are installed in accordance with
written procedures. Proof thereof will be required of
installation protocols and proof-tested holding
capacities.
- STABILITY CONSIDERATIONS.
- FOUNDATION.
- The area should be graded, leveled, and maintained so that
oil, water, drilling fluid, and other fluids will drain away
from the working area.
- Safe Bearing Capacity shall be determined from the use of
an appropriate table, soil core test, penetrometer test, flat-plate
test, or other suitable soil test. When surface conditions
are used to determine bearing capacity, care must be
exercised to insure that the soil is homogeneous to a depth
of at least twice the width of supplemental footing used to
support the concentrated load.
- Supplemental footing shall be provided to distribute the
concentrated loads from the mast and rig support points. The
manufacturer's load distribution diagram will indicate these
locations. In the absence of a manufacturer's diagram, the
supplemental footing shall be designed to carry the maximum
anticipated hook load, the gross weight of the mast, the
mast mount, the traveling equipment, and the vertical
component of guywire tension under operational loading
conditions. These footings must also support the mast and
mast weight during mast erection.
- Wellhead cellars present special foundation
considerations. In addition to the obvious ones such as
collecting water and fluids that can seep into the ground,
cellars also require unique mast support considerations.
These should be analyzed by a qualified person to insure
that an adequate mast foundation is provided.
- Small settlements (soil subsidence) at the beginning of
rig-up is considered normal. External guywires should never
be used for plumbing the mast. Rig foundations, guywire
anchors and guywire tension should be checked at each tower
(shift) change.
- GUYWIRES.
- All guywires, as indicated by the manufacturer's diagram,
should be in position and properly tensioned prior to
commencing any work. In the absence of manufacturer
recommendations, or where mast manufacturer's
recommendations cannot be implemented, the diagram in Figure
IV:1-2 may be used.
- Other guying patterns may be used; however, they
must be based on sound engineering principles as
determined by a qualified person. These
recommendations should be posted on the mast in a
weatherproof container and should state the loading
conditions for which they were prepared. Guywires
should be 6×19 or 6×37 class, regular lay, made of
improved plow steel (IPS) or better with independent
wire-rope core (IWRC) and not
previously used for any other application. Double
saddle clips should be used, and wire rope should be
installed in accordance with the manufacturer's
recommendations. In the absence of manufacturer
recommendations, API RP 9B shall be followed.
|
FIGURE IV:1-2.
ANCHOR
LOCATION DIAGRAM.
 |
- GUYWIRE ANCHORS.
- The mast manufacturer's recommendations shall be
followed. In the absence of manufacturer
recommendations the location diagram, Figure IV:1-3,
may be used.
- Each zone requires an anchor of different holding
capacity. If anchors are located in more than one
zone, then all anchors should be of the capacity
required for the greater capacity zone. For example,
if one anchor is located in "ZONE C" and
the remaining anchors are located in "ZONE
D," all anchors shall meet the holding capacity
specified in the chart for "ZONE C." See
Figure IV:1-4.
|
FIGURE
IV:1-3
RECOMMENDED
ANCHOR LOCATIONS.  |
FIGURE IV:1-4. ANCHOR CAPACITY REQUIREMENTS
FOR EACH ZONE
|
ANCHOR CAPACITY (TONS)
| Zone |
Doubles
Mast |
Singles
Mast |
Post
Mast |
| A |
15.6 |
7.0 |
7.0 |
| B |
11.5 |
5.0 |
5.0 |
| C |
9.0 |
5.0 |
5.0 |
| D |
7.4 |
5.0 |
5.0 |
Anchor Capacities shown assume
the following:
- Adequate foundation support for mast and carrier.
- Adequate crown-to-carrier internal load guys.
- Maximum wind load -- 70 mph.
- Maximum hook load, as described elsewhere in this
chapter.
- Full rod and tubing setback (N/A for Pole unit).
|
|
- OBSERVATIONS, DIRECTIONS, AND CONCLUSIONS.
- VISUAL OBSERVATIONS.
- There are characteristic visual observations that can
serve as indicators of rig stability. They include, but are
not limited to, the following:
- The foundation supports the rig, substructure, and all
applied loads while in an operational mode, without
excessive movement, basically in a level and plumb
configuration.
- No large movement is observable between the mast
support structure and the rotary/setback support
structure when the slips are set and the load is removed
from the mast, or vice versa.
- The empty travel block hangs plumb with the centerline
of the wellbore and the mast support structure remains
level.
- The mast support structure and/or substructure does
not lean to one side more than the other when the load
is applied. The guywire on one side becomes noticeably
taut while the guywire on the opposite side becomes
slack.
- The guywire anchor(s) show(s) no visible signs of
movement during the loading and unloading of the system
while in operational mode.
- The chart presented in Figure IV:1-5 may be used as a
guide to the pretensioning of guywires. This method is
commonly referred to as the Catenary Method (guywire sag
method).
FIGURE IV:1-5. CATENARY METHOD
| |
Guywire
Sag (inches) |
| |
Pole
Mast |
Single
Mast |
Double
Mast |
| Distance
Well to anchor (ft) |
Tubing
Board Guy |
Crown-
Ground Guy |
Tubing
Board Guy |
Crown-
Ground Guy |
Tubing
Board Guy |
Crown-
Ground Guy |
40
60
80
100
120 |
-
-
-
- |
4
6
10
14
18 |
4
8
15
22
32 |
4
6
10
14
18 |
6
12
17
26
32 |
5
8
11
15
21 |
| |
| Pre
tension (Pounds) |
500 |
1000 |
500 |
1000 |
500 |
1000 |
- SUPPORT MANUAL. The support manual,
entitled Guideline on the Stability of Well
Servicing Derricks, is divided into work sections and
intended to supplement this chapter. It provides a detailed
analysis of existing guides and standards along with state-of-the-art
developments.
Section 3 provides the direction and guidance necessary to
evaluate and select the proper system to assure rig stability.
Section 4 discusses the installation of guywire anchor systems. It
is extremely important to point out that stability is dependent on
the entire system, and not on a single component. In the absence
of support documentation or manufacturer specifications, Section 6
sets forth the criteria for performing effective pull testing. It
further identifies what would be acceptable in lieu of actual pull
testing.
- CONCLUSION.
- No set of observations or recommendations should be so
restrictive or subjective as to preclude the use of innovative
approaches to derrick stability systems. Properly designed
substructures and base beams have been used effectively and
safely as anchorages for guywires.
- Engineering calculations based on sound engineering
principles may also be used as evidence of an acceptable
alternative to pull testing. Dead weight of equipment,
fabricated components (i.e. padeyes) and other appurtenances
are all considerations in determining rig stability.
- The derrick manufacturer's specifications and
recommendations should be the preferred and primary means of
determining derrick stability. Guywire anchors, newly
installed according to the manufacturer's specifications, may
be used without the requirement for actual pull testing. (This
would qualify as meeting the criteria as an acceptable
alternative to pull testing.) If, however, there is a change
in conditions, e.g. frozen ground to thawed ground, or if use
of the anchor has been interrupted, the anchor shall be pull
tested, with documentation thereof, prior to being placed back
in service.
- BIBLIOGRAPHY.
American Petroleum Institute (API). 1988. Specification
4E: Specification for Drilling and Well Servicing Structures.
API: Washington, D.C.
Association of Oilwell Servicing Contractors (AOSC). 1988. Recommended
Safe Procedures and Guidelines for Oil and Gas Well Servicing.
AOSC: Dallas.
International Association of Drilling Contractors (IADC). 1990. Accident
Prevention Manual. IADC: Houston.
International Association of Drilling Contractors. 1979. Drilling
Manual. IADC: Houston.
Scardino, A.J. 1990. Guidelines on the Stability
of Well Servicing Derricks. Sigma Associates Ltd.: Pass
Christian, MS.
|